Quantcast

North Lake Times

Friday, May 3, 2024

U.S. Hwy 27/441 Widening Project

Road

construction | unsplash by Troy Mortier

construction | unsplash by Troy Mortier

The Florida Department of Transportation (FDOT) is widening U.S. 441 from four to six lanes between Lake Ella Road and Avenida Central (at Griffin Avenue) 

in Lady Lake. The purpose of this project is to provide safety and operational enhancements for drivers and pedestrians. This project will begin extensive work around the County Road 25 overpass.

The northbound U.S. 441 bridge is being removed and all embankments are being excavated. There is continuous work on widening the outside northbound lane between Fennell Boulevard and Avenida Central. The traffic signals at the intersection of Old Vineyard are being reconstructed. The widening of the southbound roadway between Griffin View Drive and Lake Ella Road is underway, and additional drainage, sidewalk and other roadway improvements are being made.

Demolition of the existing curb, gutter and sidewalks going northbound between East Lake View Street and Lemon Street has begun Additionally, the project team is working on adding a right turn lane at the light on Fennell Boulevard, as well as temporarily repaving the Water Oaks Community entrance. The estimated completion date is January 2024.

All construction is contingent upon weather and material being available for the project. Information is also available on the project website at www.cflroads.com/project/238395-5.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS