Quantcast

North Lake Times

Thursday, November 21, 2024

Streetscape Phase 3 – Construction Update

22

Update | Pexels by Anna Tarazevich

Update | Pexels by Anna Tarazevich

Work on the third and final phase of the Streetscape project resumed Monday after the holiday season. Crews closed the intersection of W. Montrose and Lake Avenue, Section 5, and began removing the old asphalt.  Underground utilities will be upgraded, and brick pavers will be added. Work is expected to take about four weeks to complete.

 The focus will then move to 7th Street between W. Montrose Street and Minneola Avenue – Sections 6 and 7 - and take about four months to complete.

 Access to businesses and parking will remain during the work, and traffic will be routed around the active work areas. As with any construction project, weather or other unforeseen conditions could impact the schedule, including supply chain/material delays.  

 Please see the map below for a complete overview and timeframe.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS